New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

The Open Group Exam OGEA-103 Topic 1 Question 23 Discussion

Actual exam question for The Open Group's OGEA-103 exam
Question #: 23
Topic #: 1
[All OGEA-103 Questions]

Please read this scenario prior to answering the question

Your role is that of a consultant to the Lead Enterprise Architect in a multinational automotive manufacturer.

The company has a corporate strategy that focuses on electrification of its portfolio, and it has invested

heavily in a new shared car platform to use across all its brands. The company has four manufacturing

facilities, one in North America, two in Europe, and one in Asia.

A challenge that the company is facing is to scale up the number of vehicles coming off the production line to meet customer demand, while maintaining quality. There are significant supply chain shortages for electronic components, which are impacting production. In response to this the company has taken on new suppliers and has also taken design and production of the battery pack in-house.

The company has a mature Enterprise Architecture practice. The TOGAF standard is used for developing

the process and systems used to design, manufacture, and test the battery pack. The Chief Information

Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.

As part of putting the new battery pack into production, adjustments to the assembly processes need to be made. A pilot project has been completed at a single location. The Chief Engineer, sponsor of the activity, and the Architecture Board have approved the plan for implementation and migration at each plant.

Draft Architecture Contracts have been developed that detail the work needed to implement and deploy the new processes for each location. The company mixes internal teams with a few third-party contractors at the locations. The Chief Engineer has expressed concern that the deployment will not be consistent and of acceptable quality.

Refer to the scenario

The Lead Enterprise Architect has asked you to review the draft Architecture Contracts and recommend the best approach to address the Chief Engineer's concern.

Based on the TOGAF Standard, which of the following is the best answer?

Show Suggested Answer Hide Answer
Suggested Answer: C

According to the TOGAF Standard, Version 9.2, anArchitecture Contractis a joint agreement between development partners and sponsors on the deliverables, quality, and fitness-for-purpose of an architecture1.It defines the scope, responsibilities, and governance of the architecture work, and ensures the alignment and compliance of the architecture with the business goals and objectives1.

In the scenario, the Lead Enterprise Architect has asked you to review the draft Architecture Contracts and recommend the best approach to address the Chief Engineer's concern about the consistency and quality of the deployment of the new processes for the battery pack production at each location.

The best answer is C, because it follows the guidelines and best practices for defining and using Architecture Contracts as described in the TOGAF Standard, Version 9.22. It ensures that the contracts cover the essential aspects of the project objectives, effectiveness metrics, acceptance criteria, and risk management, and that they are legally enforceable for third-party contractors. It also recommends a schedule of compliance reviews at key points in the implementation process, and a mechanism for handling any deviations from the Architecture Contract, involving the Architecture Board and the possibility of granting a dispensation to allow the process to be customized for local needs.

The other options are not correct because they either23:

A) For changes requested by an internal team, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to third-party contractors, you recommend that it is a fully enforceable legal contract. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.: This option does not address the need to review the contracts to ensure that they address the project objectives, effectiveness metrics, acceptance criteria, and risk management. It also does not recommend a schedule of compliance reviews at key points in the implementation process. Moreover, it suggests that a memorandum of understanding is sufficient for internal teams, which may not be legally binding or enforceable.

B) For changes undertaken by internal teams, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. If a contract is issued to a contractor, you recommend that it is a fully enforceable legal contract. If a deviation from the Architecture Contract is found, you recommend that the Architecture Board grant a dispensation to allow the implementation organization to customize the process to meet their local needs.: This option has the same problems as option A, and also implies that the Architecture Board should always grant a dispensation for any deviation, which may not be appropriate or desirable in some cases.

D) You recommend that the Architecture Contracts be used to manage the architecture governance processes across the locations. You recommend deployment of monitoring tools to assess the performance of each completed battery pack at each location and develop change requirements if necessary. If a deviation from the contract is detected, the Architecture Board should allow the Architecture Contract to be modified meet the local needs. In such cases they should issue a new Request for Architecture Work.: This option does not address the need to review the contracts to ensure that they address the project objectives, effectiveness metrics, acceptance criteria, and risk management. It also does not recommend a schedule of compliance reviews at key points in the implementation process. Moreover, it suggests that the Architecture Board should always allow the Architecture Contract to be modified for any deviation, which may not be appropriate or desirable in some cases. It also implies that a new Request for Architecture Work should be issued for each deviation, which may not be necessary or feasible.


1: The TOGAF Standard, Version 9.2, Chapter 3: Definitions and Terminology, Section 3.1: Terms and Definitions

2: The TOGAF Standard, Version 9.2, Chapter 43: Architecture Contracts

3: The TOGAF Standard, Version 9.2, Chapter 44: Architecture Governance

Contribute your Thoughts:

Ben
6 months ago
Both options seem valid. Ensuring compliance and adapting to local needs is key.
upvoted 0 times
...
Ben
6 months ago
True, but D seems thorough too. Deploying monitoring tools would be beneficial for quality control.
upvoted 0 times
...
Kristine
7 months ago
Yeah, and it also involves legal enforceability for third-party contracts.
upvoted 0 times
...
Johnathon
7 months ago
I think option C makes the most sense. It covers project objectives, effectiveness, and risk management.
upvoted 0 times
...
Letha
7 months ago
Agreed, managing such large-scale architecture changes must be super challenging.
upvoted 0 times
...
Ben
7 months ago
Wow, this scenario is intense!
upvoted 0 times
...

Save Cancel