Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ServiceNow Exam CIS-SPM Topic 6 Question 34 Discussion

Actual exam question for ServiceNow's CIS-SPM exam
Question #: 34
Topic #: 6
[All CIS-SPM Questions]

If an it_project_manager does not want to equally distribute hours across the resource plan time frame, what allocation spread should be used?

Show Suggested Answer Hide Answer
Suggested Answer: B

If an it_project_manager does not want to equally distribute hours across the resource plan time frame, the allocation spread should be set to Any. This option allows the it_project_manager to manually enter the hours for each month or quarter in the resource plan. The other options (Even, Back Load, and Front Load) automatically distribute the hours evenly, from the end, or from the start of the time frame, respectively. You can find more information about the allocation spread in theProduct Documentationfor ServiceNow.


Contribute your Thoughts:

Oren
3 days ago
I think the answer is Front Load.
upvoted 0 times
...
Derick
6 days ago
Whoa, 'Any' allocation? That's like a free-for-all, and I'm not feeling that at all.
upvoted 0 times
...
Vesta
13 days ago
I'm feeling a 'Front Load' kind of vibe. Get it all done early and then kick back with a cold one!
upvoted 0 times
...
Kenneth
18 days ago
C'mon, 'Back Load' is the way to go! It's like saving the best for last, right?
upvoted 0 times
...

Save Cancel