What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

Show Suggested Answer Hide Answer
Suggested Answer: C

A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in theProduct Documentationfor ServiceNow.


Contribute your Thoughts:

Shay
25 days ago
Baseline, of course. Though I did consider D) Forecast for a second - it would be nice to have a crystal ball for the project, am I right?
upvoted 0 times
Pamella
7 days ago
Yeah, Forecast would be great if we could predict the future, but Baseline is more practical.
upvoted 0 times
...
Marshall
12 days ago
Baseline is definitely the way to go for comparison reporting later.
upvoted 0 times
...
...
Evette
28 days ago
I believe it's C) Baseline because it's a snapshot of the project at a specific point in time.
upvoted 0 times
...
Catrice
1 months ago
C) Baseline, obviously. What is this, an easy question? I could do this in my sleep.
upvoted 0 times
...
Ettie
1 months ago
I'm not sure, but I think it's between C) Baseline and D) Forecast.
upvoted 0 times
...
Cherry
1 months ago
Hmm, I was between C) Baseline and D) Forecast. But Baseline seems like the more accurate choice for a data copy of the current project.
upvoted 0 times
Rutha
16 days ago
Yeah, Baseline is the most accurate choice for this scenario.
upvoted 0 times
...
Candida
17 days ago
Baseline is definitely the best option for that.
upvoted 0 times
...
Thersa
17 days ago
I agree, Baseline is used for comparison reporting later.
upvoted 0 times
...
Alise
21 days ago
I think C) Baseline is the correct choice for a data copy of the current project.
upvoted 0 times
...
...
Dacia
1 months ago
I agree with Melissa, Baseline makes sense for comparison reporting.
upvoted 0 times
...
Melissa
1 months ago
I think the answer is C) Baseline.
upvoted 0 times
...
Jaime
2 months ago
Baseline makes the most sense to me. It's like a freeze-frame of the project that you can look back on.
upvoted 0 times
Keneth
1 months ago
I agree, baseline is definitely the best option for comparison reporting later.
upvoted 0 times
...
Gene
1 months ago
Baseline makes the most sense to me. It's like a freeze-frame of the project that you can look back on.
upvoted 0 times
...
...
Deeanna
2 months ago
I think the answer is C) Baseline. It's a snapshot of the project's current state that can be used for tracking and comparison later.
upvoted 0 times
Lina
1 months ago
No, it's definitely C) Baseline. It's like a benchmark for the project's performance.
upvoted 0 times
...
Dalene
1 months ago
I think it might be D) Forecast, as it predicts future outcomes based on current data.
upvoted 0 times
...
Lorrie
2 months ago
I agree, the answer is C) Baseline. It serves as a reference point for measuring progress.
upvoted 0 times
...
...

Save Cancel