Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ServiceNow Exam CIS-SPM Topic 4 Question 30 Discussion

Actual exam question for ServiceNow's CIS-SPM exam
Question #: 30
Topic #: 4
[All CIS-SPM Questions]

What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

Show Suggested Answer Hide Answer
Suggested Answer: C

A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in theProduct Documentationfor ServiceNow.


Contribute your Thoughts:

Colby
2 days ago
C) Baseline is the way to go. Gotta have that reference point to see how things are progressing, am I right?
upvoted 0 times
...
Noble
4 days ago
I was tempted to go with D) Forecast, but I think C) Baseline is the better option. It's a more accurate representation of the current state.
upvoted 0 times
...
Nilsa
12 days ago
Baseline definitely sounds like the right choice here. It's a data copy that can be used as a reference point.
upvoted 0 times
...
German
24 days ago
I think C) Baseline is the correct answer. It's a snapshot of the project that can be used for comparison later.
upvoted 0 times
Stephaine
4 days ago
I agree, C) Baseline is the correct answer. It helps track progress.
upvoted 0 times
...
Meaghan
5 days ago
Yes, C) Baseline is like a reference point for comparison in the future.
upvoted 0 times
...
...
Laine
1 months ago
I believe it's C) Baseline because it serves as a reference point for comparison.
upvoted 0 times
...
Maynard
1 months ago
I'm not sure, but I think it's either A) Accrual or C) Baseline.
upvoted 0 times
...
Shantell
1 months ago
I think the answer is C) Baseline.
upvoted 0 times
...
Julene
1 months ago
I agree with Shantell, Baseline makes sense for comparison reporting.
upvoted 0 times
...

Save Cancel