BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ServiceNow Exam CIS-SPM Topic 1 Question 1 Discussion

Actual exam question for ServiceNow's CIS-SPM exam
Question #: 1
Topic #: 1
[All CIS-SPM Questions]

What is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later?

Show Suggested Answer Hide Answer
Suggested Answer: C

A baseline is a data copy of the current project's task, schedule, or structure that can be used for comparison reporting later. A baseline captures the original plan of the project and allows you to track the changes and deviations from the plan over time. You can create multiple baselines for a project and compare them with the current state of the project. You can find more information about baselines in theProduct Documentationfor ServiceNow.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel