ScrumStudy Exam SMC Topic 2 Question 105 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 105
Topic #: 2
[All SMC Questions]

You are the Scrum Master of the JKM Project and your Development Team has asked to change some rules about the duration of the Sprints. Which one of the following statements is a rule of Scrum that the team should follow when it comes to Sprint duration?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Malika
2 months ago
D) Multiple Scrum teams can start their Sprints as soon as the Development Team is assembled? Really? That sounds like a recipe for chaos. Scrum is all about timing and coordination.
upvoted 0 times
...
Daniela
2 months ago
C is the way to go. Though I do like the idea of starting on a Tuesday - Mondays are so overrated.
upvoted 0 times
Annett
15 days ago
Definitely, it helps maintain focus and predictability.
upvoted 0 times
...
Steffanie
21 days ago
Agreed, consistency is key in Scrum.
upvoted 0 times
...
Louvenia
24 days ago
The Sprint duration should not change once the project begins.
upvoted 0 times
...
Lilli
1 months ago
C is the way to go. Though I do like the idea of starting on a Tuesday - Mondays are so overrated.
upvoted 0 times
...
...
Weldon
2 months ago
I agree with Bernardo. Changing the Sprint duration mid-project would be like changing the rules of the game after it's already started. Not cool, man.
upvoted 0 times
...
Bernardo
2 months ago
C) The Sprint duration should not change once the project begins. This is a core Scrum rule that teams must follow for consistency and predictability.
upvoted 0 times
Candra
1 months ago
D) Multiple Scrum teams, in one project, can start their Sprints as soon as the Development Team is assembled.
upvoted 0 times
...
Amber
2 months ago
A) Multiple Scrum teams can have sprints of different duration in one project.
upvoted 0 times
...
...
Makeda
2 months ago
I disagree, I think option A) Multiple Scrum teams can have sprints of different duration in one project is valid as long as it works for the team and project goals.
upvoted 0 times
...
Felice
2 months ago
I agree with Lynsey, changing the Sprint duration mid-project can disrupt the team's rhythm and impact the project's success.
upvoted 0 times
...
Lynsey
3 months ago
I think the rule of Scrum that the team should follow is C) The Sprint duration should not change once the project begins.
upvoted 0 times
...