While assisting the Product Owner in developing a Prioritized Product Backlog, the Scrum Master must
consider the primary factors on which the Prioritized Product Backlog is based-on. Which of the following are those primary factors?
A) Value
B) Dependencies
C) Risk
D) Deliverables
The Prioritized Product Backlog contains a prioritized list of business and project requirements written in the form of Epic(s), which are high level User Stories. The Prioritized Product Backlog is based on three primary factors: value, risk or uncertainty, and dependencies. It is also referred to as the Risk Adjusted Product Backlog since it includes identified and assessed risks related to the project.
http://blog.scrumstudy.com/prioritized-product-backlog-the-backbone-of-a-scrum-project/
Gearldine
4 months agoEdna
4 months agoSamira
4 months agoTrina
5 months agoCorazon
5 months agoLaquita
5 months agoTonja
5 months agoIlene
5 months agoNickolas
5 months agoElenora
5 months agoGilma
5 months ago