BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ScrumStudy Exam SMC Topic 1 Question 37 Discussion

Actual exam question for ScrumStudy's SMC exam
Question #: 37
Topic #: 1
[All SMC Questions]

Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to

your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories

committed to for the current Sprint because the customer has changed a critical business requirement. Which

one of the following statements presents the best solution for such a situation?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel