Scaled Agile Exam SAFe-SPC Topic 4 Question 15 Discussion

Actual exam question for Scaled Agile's SAFe-SPC exam
Question #: 15
Topic #: 4
[All SAFe-SPC Questions]

(Select 2) What activity does NOT happen on Day 1 of PI Planning?

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Quinn
5 months ago
Alright, C) Management review and problem-solving meeting, and E) Hourly checkpoints it is.
upvoted 0 times
...
Lonny
5 months ago
Team breakouts definitely happen on the first day for planning. Let's stick with C) and E).
upvoted 0 times
...
Melynda
5 months ago
ROAMing of risks does happen on Day 1. I'm sure of that. What about D) Team breakouts?
upvoted 0 times
...
Ahmed
6 months ago
I agree with E) Hourly checkpoints because it's more of an ongoing activity. But what about ROAMing of risks?
upvoted 0 times
...
Glendora
6 months ago
I feel C) Management review and problem-solving meeting and E) Hourly checkpoints don't happen on Day 1.
upvoted 0 times
...
Quinn
6 months ago
The question seems tricky. What do you think doesn't happen on Day 1 of PI Planning?
upvoted 0 times
...