You are performing an SAP S/4HANA conversion for your production system. This conversion requires that certain business functions are switched on.
Following SAP recommendations, how will you achieve this?
There are 2 correct answers to this question.
Response:
You are planning an SAP S/4HANA conversion.
Which conversion-specific tasks must be performed during the preparation phase?
You are preparing for a standard SAP S/4HANA conversion from SAP ECC on Windows with SAP MaxDB to SAP S/4HAN. You are performing the corresponding maintenance transaction with the Maintenance Planner. Which kernels do you need to select for the SAP S/4HANA conversion?
There are 2 correct answers to this question.
You are performing an SAP S/4HANA conversion. You are in the BIND_PATCH phase of the Configuration roadmap step. For some software components, you find entries in the Calculated level column. What does the Calculated level indicate for those software components?
You are performing an inplace SAP S/4HANA conversion including DMO. What is the latest point in time when you can reset the procedure without losing data?
Fausto
2 days agoOdette
6 days agoCrissy
18 days agoDerick
19 days agoOneida
21 days agoGladys
1 months agoMica
1 months agoDella
2 months agoVenita
2 months agoCurt
2 months agoVernice
2 months agoRachael
2 months agoMelinda
3 months agoJacklyn
3 months agoSkye
4 months agoEllsworth
4 months agoMel
5 months agoSon
5 months agoAlica
5 months agoSusana
6 months agoNobuko
6 months agoCordelia
6 months ago