SAP Exam E_ACTAI_2403 Topic 4 Question 23 Discussion

Actual exam question for SAP's E_ACTAI_2403 exam
Question #: 23
Topic #: 4
[All E_ACTAI_2403 Questions]

What should the project team consider when defining their sprint duration and cadence? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

Chantell
1 days ago
Adjusting the sprint duration based on team availability is a smart move, it helps accommodate any unforeseen changes.
upvoted 0 times
...
Gertude
15 days ago
I think the sprint duration should be fixed, it's easier to keep track of the progress that way.
upvoted 0 times
Royal
5 days ago
D) Establish fixed duration of each sprint.
upvoted 0 times
...
Vincent
6 days ago
A) Sprint duration between 1 week to 4 weeks.
upvoted 0 times
...
...
Ivory
19 days ago
I agree with Jettie. Adjusting sprint duration based on team availability is important for successful project delivery.
upvoted 0 times
...
Jettie
26 days ago
I think the project team should consider the team availability.
upvoted 0 times
...