Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam E_ACTAI_2403 Topic 4 Question 23 Discussion

Actual exam question for SAP's E_ACTAI_2403 exam
Question #: 23
Topic #: 4
[All E_ACTAI_2403 Questions]

What should the project team consider when defining their sprint duration and cadence? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

Darell
2 months ago
Haha, 'set variable sprint duration based on work' - that's like trying to herd cats!
upvoted 0 times
Crista
1 months ago
D) Establish fixed duration of each sprint.
upvoted 0 times
...
Ettie
1 months ago
C) Haha, it can be challenging to set variable sprint duration based on work!
upvoted 0 times
...
Chantay
1 months ago
B) Adjust sprint duration based on team availability.
upvoted 0 times
...
Truman
1 months ago
A) Sprint duration between 1 week to 4 weeks.
upvoted 0 times
...
...
Matt
2 months ago
Variable sprint duration sounds like a recipe for chaos. I'd go with a consistent cadence for the team.
upvoted 0 times
Melvin
26 days ago
B) Adjust sprint duration based on team availability.
upvoted 0 times
...
Keva
28 days ago
Variable sprint duration can work if managed properly.
upvoted 0 times
...
Cassi
1 months ago
D) Establish fixed duration of each sprint.
upvoted 0 times
...
Quiana
2 months ago
A) Sprint duration between 1 week to 4 weeks.
upvoted 0 times
...
...
Chantell
2 months ago
Adjusting the sprint duration based on team availability is a smart move, it helps accommodate any unforeseen changes.
upvoted 0 times
Lashawnda
1 months ago
D) Establish fixed duration of each sprint.
upvoted 0 times
...
Lai
1 months ago
Yes, it's important to be flexible with sprint duration to account for team availability.
upvoted 0 times
...
Florinda
1 months ago
B) Adjust sprint duration based on team availability.
upvoted 0 times
...
Stephane
2 months ago
A) Sprint duration between 1 week to 4 weeks.
upvoted 0 times
...
...
Gertude
3 months ago
I think the sprint duration should be fixed, it's easier to keep track of the progress that way.
upvoted 0 times
Nicholle
2 months ago
B) Adjust sprint duration based on team availability.
upvoted 0 times
...
Kiera
2 months ago
I agree, having a fixed duration makes it easier to track progress.
upvoted 0 times
...
Royal
2 months ago
D) Establish fixed duration of each sprint.
upvoted 0 times
...
Vincent
2 months ago
A) Sprint duration between 1 week to 4 weeks.
upvoted 0 times
...
...
Ivory
3 months ago
I agree with Jettie. Adjusting sprint duration based on team availability is important for successful project delivery.
upvoted 0 times
...
Jettie
3 months ago
I think the project team should consider the team availability.
upvoted 0 times
...

Save Cancel