BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam E_ACTAI_2403 Topic 1 Question 6 Discussion

Actual exam question for SAP's E_ACTAI_2403 exam
Question #: 6
Topic #: 1
[All E_ACTAI_2403 Questions]

What should the project team consider when defining their sprint duration and cadence? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, C

Contribute your Thoughts:

Venita
5 months ago
So, you guys think it's A and D? Sounds reasonable. I'll go with that.
upvoted 0 times
...
Kaitlyn
5 months ago
Yeah, D makes sense. Consistent sprint lengths make planning easier.
upvoted 0 times
...
Marleen
5 months ago
I reckon D is also correct. Establishing a fixed duration helps with consistency.
upvoted 0 times
...
Gerald
6 months ago
I agree with A. It's a standard range. But what about the other answer?
upvoted 0 times
...
Keshia
6 months ago
Haha, I'd love to see a project manager try to set 'variable sprint duration based on work'. That sounds like a recipe for chaos!
upvoted 0 times
...
Laurel
6 months ago
I agree with B and D. Adjusting sprints to accommodate the team's capacity and keeping a consistent duration are important factors to consider.
upvoted 0 times
...
Lina
6 months ago
Definitely B and D. Flexibility in sprint duration based on team constraints and maintaining a consistent cadence are essential for effective sprint planning.
upvoted 0 times
Lauran
5 months ago
D
upvoted 0 times
...
Fannie
6 months ago
B
upvoted 0 times
...
...
Jess
6 months ago
I think B and D are the correct answers. Adjusting sprint duration based on team availability and having a fixed duration for each sprint are crucial for project management.
upvoted 0 times
...
Shenika
6 months ago
I feel the same way. But I think one correct answer is A. Sprint duration between 1 week to 4 weeks sounds about right.
upvoted 0 times
...
Venita
6 months ago
I really don't like questions about sprint duration. They seem tricky.
upvoted 0 times
...
Omer
7 months ago
Adjust sprint duration based on team availability.
upvoted 0 times
...
Dong
7 months ago
Sprint duration between 1 week to 4 weeks.
upvoted 0 times
...
Mabelle
7 months ago
What should the project team consider when defining their sprint duration and cadence?
upvoted 0 times
...

Save Cancel