SAP Exam Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Topic 2 Question 63 Discussion

Actual exam question for SAP's Production Planning & Manufacturing with SAP ERP 6.0 EHP7 exam
Question #: 63
Topic #: 2
[All Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Questions]

The stock/requirements list for a finished product contains only one sales order and one fixed planned order with the same quantity. The availability dates for both MRP elements are on working days. The availability date for the fixed planned order is set to a later date than the one for the sales order.

However, a corresponding rescheduling exception message does not appear.

What could be the reasons? (Choose two)

Show Suggested Answer Hide Answer
Suggested Answer: A, B