BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Topic 2 Question 22 Discussion

Actual exam question for SAP's Production Planning & Manufacturing with SAP ERP 6.0 EHP7 exam
Question #: 22
Topic #: 2
[All Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Questions]

Your customer tests the firming options for planned orders in SAP ECC using a test material. Therefore, the customer sets a firming date in the stock/requirements list manually. Additionally, the customer sets a planning time fence with firming type 1 in the material master.

How is the resulting firming interval specified in this scenario?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel