New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Topic 1 Question 53 Discussion

Actual exam question for SAP's Production Planning & Manufacturing with SAP ERP 6.0 EHP7 exam
Question #: 53
Topic #: 1
[All Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Questions]

An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default. However, some materials are to be given a different planning horizon.

What procedure would you recommend to the project team for setting the planning horizon on the system side?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel