In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00
a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?