Question #: 3
Topic #: 1
[All Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Questions]

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40.

Which sequence category do you use to create the second sequence in the system?

Show Suggested Answer Hide Answer
Suggested Answer: D