BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Topic 1 Question 3 Discussion

Actual exam question for SAP's Production Planning & Manufacturing with SAP ERP 6.0 EHP7 exam
Question #: 3
Topic #: 1
[All Production Planning & Manufacturing with SAP ERP 6.0 EHP7 Questions]

You create a routing that includes five operations in an initial sequence (10, 20, 30, 40, 50). When capacity bottlenecks occur, you want to use a second sequence on other work centers for operations 30 and 40.

Which sequence category do you use to create the second sequence in the system?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel