Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS422_2023 Topic 9 Question 19 Discussion

Actual exam question for SAP's C_TS422_2023 exam
Question #: 19
Topic #: 9
[All C_TS422_2023 Questions]

What could be the reason for multiple commitments where several operations have the same scheduled dates on a work center after dispatching? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Catarina
28 days ago
I'm going with B and C. Seems like the most logical explanation for the problem. Although, I do wonder if the test writers have a sense of humor... 'Finite Scheduling' - really?
upvoted 0 times
...
Raina
1 months ago
Haha, I bet the person who wrote this question was just having a laugh. 'Finite Scheduling' and 'Change Planning Direction' - sounds like they're trying to trip us up!
upvoted 0 times
Quentin
7 days ago
B) The work center has several individual capacities.
upvoted 0 times
...
Juan
15 days ago
A) The Finite Scheduling indicator is NOT set in the strategy profile.
upvoted 0 times
...
...
Lavonne
1 months ago
D is also a valid answer. The Change Planning Direction indicator can affect the scheduling and cause multiple commitments on the same dates.
upvoted 0 times
Alex
18 days ago
D) The Change Planning Direction indicator is set in the strategy profile.
upvoted 0 times
...
Shanda
20 days ago
B) The work center has several individual capacities.
upvoted 0 times
...
Candra
26 days ago
A) The Finite Scheduling indicator is NOT set in the strategy profile.
upvoted 0 times
...
...
Roy
1 months ago
I think both A) and D) could be the reasons, depending on the specific scenario.
upvoted 0 times
...
Lavelle
2 months ago
I believe another reason could be D) The Change Planning Direction indicator is set in the strategy profile.
upvoted 0 times
...
Jody
2 months ago
I think the correct answers are B and C. The work center having multiple individual capacities and the alternative work centers being fully occupied can both lead to multiple commitments on the same scheduled dates.
upvoted 0 times
Phyliss
1 months ago
Exactly, those two reasons can explain why there are multiple commitments with the same scheduled dates on a work center.
upvoted 0 times
...
Temeka
1 months ago
So, it seems like the correct answers are B and C then.
upvoted 0 times
...
Louvenia
2 months ago
Yes, that makes sense. And if the alternative work centers are fully occupied, it would also lead to the same scheduled dates for operations.
upvoted 0 times
...
Alaine
2 months ago
I agree, having multiple individual capacities at the work center can definitely cause multiple commitments.
upvoted 0 times
...
...
Alva
2 months ago
I agree with Broderick, that could definitely cause multiple commitments on the same date.
upvoted 0 times
...
Broderick
2 months ago
I think the reason could be A) The Finite Scheduling indicator is NOT set in the strategy profile.
upvoted 0 times
...

Save Cancel