SAP Exam C_TS422_2023 Topic 3 Question 17 Discussion

Actual exam question for SAP's C_TS422_2023 exam
Question #: 17
Topic #: 3
[All C_TS422_2023 Questions]

Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Muriel
3 months ago
Option A seems too obvious, and C is a bit of a stretch. I'm gonna have to go with B on this one. Gotta love those alternative resources!
upvoted 0 times
Sabrina
1 months ago
Definitely, mode selection can have a big impact on scheduling in SAP S/4HANA Cloud Private Edition.
upvoted 0 times
...
Margot
1 months ago
I think it's important to consider all the options before making a decision.
upvoted 0 times
...
Mayra
1 months ago
Yeah, using alternative resources within one operation can be really helpful.
upvoted 0 times
...
Denae
1 months ago
I agree, option B does seem like the most logical choice.
upvoted 0 times
...
...
Kerrie
3 months ago
Haha, this question is a real brain-teaser! I'm going to go with C, just to keep things interesting.
upvoted 0 times
Bambi
2 months ago
D) When multiple planned orders are scheduled in parallel on one resource
upvoted 0 times
...
Georgeanna
2 months ago
C) When several production versions are maintained for one product
upvoted 0 times
...
Darell
2 months ago
B) When alternative resources are used within one operation
upvoted 0 times
...
Shaun
2 months ago
A) When several operations are maintained for one product
upvoted 0 times
...
...
Ashley
3 months ago
Hmm, I'm not sure. Maybe option D? Scheduling multiple planned orders in parallel on one resource sounds like a good fit for mode selection.
upvoted 0 times
...
Nadine
3 months ago
I think option B is the correct answer. Using alternative resources within an operation is a key use case for mode selection in Advanced Planning.
upvoted 0 times
Richelle
2 months ago
Actually, I believe option A is the correct answer. It makes sense to use mode selection when several operations are maintained for one product.
upvoted 0 times
...
Gayla
2 months ago
I think it could also be option D, when multiple planned orders are scheduled in parallel on one resource.
upvoted 0 times
...
Micaela
3 months ago
I agree, option B is the correct answer. It allows for flexibility in resource allocation.
upvoted 0 times
...
...
Alline
3 months ago
I agree with Beata. Mode selection is definitely needed in that scenario.
upvoted 0 times
...
Beata
4 months ago
I think you can use mode selection when several operations are maintained for one product.
upvoted 0 times
...

Save Cancel