BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS422_2023 Topic 2 Question 9 Discussion

Actual exam question for SAP's C_TS422_2023 exam
Question #: 9
Topic #: 2
[All C_TS422_2023 Questions]

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?

Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Backward scheduling is a method of determining the order dates for components from dependent requirements by starting from the requirement date of the finished product and working backwards through the production structure. Backward scheduling considers the following time elements:

Operation duration: This is the time required to perform an operation on a resource, such as a work center or a machine. Operation duration is influenced by various factors, such as the quantity, the lot size, the setup time, the processing time, the teardown time, and the operation scrap. Operation duration is subtracted from the requirement date of the finished product to determine the start date of the operation.

In-house production time: This is the time required to produce a material in-house, from the start of the first operation to the end of the last operation. In-house production time is influenced by various factors, such as the routing, the work center, the production version, and the scheduling margin key. In-house production time is subtracted from the start date of the first operation to determine the order start date of the material.

Backward scheduling does not consider the following time elements:

Total replenishment lead time: This is the time required to procure a material externally, from the creation of the purchase requisition to the receipt of the goods. Total replenishment lead time is influenced by various factors, such as the planned delivery time, the goods receipt processing time, the release time, and the scheduling margin key. Total replenishment lead time is used in forward scheduling, not backward scheduling, to determine the order dates for externally procured materials.

Planned delivery time: This is the time required to deliver a material from the vendor to the receiving plant. Planned delivery time is maintained in the purchasing info record or the material master record. Planned delivery time is a component of the total replenishment lead time, which is used in forward scheduling, not backward scheduling, to determine the order dates for externally procured materials.Reference:Backward Scheduling | SAP Help Portal,Scheduling | SAP Help Portal,SAP S/4HANA Production Planning and Manufacturing Certification Guide, page 77-78.


Contribute your Thoughts:

Cherrie
3 months ago
I see where you're coming from, Maryanne. But I think MRP mainly focuses on total replenishment lead time and in-house production time for order dates.
upvoted 0 times
...
Maryanne
3 months ago
I believe operation duration and planned delivery time are also important factors in backward scheduling.
upvoted 0 times
...
Glenn
3 months ago
I agree with Yolando. Those two elements are crucial for determining order dates accurately.
upvoted 0 times
...
Yolando
3 months ago
I think MRP considers total replenishment lead time and in-house production time.
upvoted 0 times
...
Cletus
3 months ago
In-house production time? Psh, that's only half the battle. What about the time it takes to wrangle the delivery guy?
upvoted 0 times
...
Marleen
3 months ago
I believe operation duration and planned delivery time are not considered in backward scheduling, as they are not directly related to dependent requirements.
upvoted 0 times
...
Arthur
3 months ago
Planned delivery time? Seriously? That's like trying to predict the weather a month in advance.
upvoted 0 times
Delmy
3 months ago
Planned delivery time is considered in MRP for backward scheduling.
upvoted 0 times
...
Terina
3 months ago
D) In-house production time
upvoted 0 times
...
Sarah
3 months ago
A) Total replenishment lead time
upvoted 0 times
...
...
Benedict
3 months ago
I'm not sure about operation duration and planned delivery time, do they play a role in determining order dates?
upvoted 0 times
...
Dalene
3 months ago
Total replenishment lead time and operation duration - that's a no-brainer! MRP is all about timing the orders just right.
upvoted 0 times
Adelina
2 months ago
D) In-house production time
upvoted 0 times
...
Lauran
3 months ago
C) Planned delivery time
upvoted 0 times
...
Craig
3 months ago
B) Operation duration
upvoted 0 times
...
Izetta
3 months ago
A) Total replenishment lead time
upvoted 0 times
...
...
Veronika
3 months ago
I agree with Jules, those two time elements are crucial for backward scheduling in MRP.
upvoted 0 times
...
Jules
4 months ago
I think MRP considers total replenishment lead time and in-house production time.
upvoted 0 times
...

Save Cancel