BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS422_2022 Topic 8 Question 25 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 25
Topic #: 8
[All C_TS422_2022 Questions]

Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Sharita
1 months ago
B) Planning with final assembly is the way to go. Gotta love those last-minute orders that keep us on our toes. It's like a surprise party, but with more spreadsheets!
upvoted 0 times
Sabine
10 days ago
A) Make-to-stock production (10)
upvoted 0 times
...
...
Phung
1 months ago
I'm going with D) Planning without final assembly. Who needs a final assembly when you can just sell the raw materials, am I right? *wink wink*
upvoted 0 times
...
Bettina
1 months ago
But with make-to-stock production, the finished goods are produced based on forecasted demand, ensuring they are in stock when customers order.
upvoted 0 times
...
Ahmad
1 months ago
I disagree, I believe the correct answer is B) Planning with final assembly.
upvoted 0 times
...
Luis
1 months ago
C) Make-to-stock production sounds like the right choice. Keeping the goods in stock and ready to ship is the best way to handle unexpected orders.
upvoted 0 times
Lavonda
5 days ago
C) Make-to-stock production (20)
upvoted 0 times
...
An
20 days ago
B) Planning with final assembly (40)
upvoted 0 times
...
Anthony
22 days ago
A) Make-to-stock production (10)
upvoted 0 times
...
...
Alease
1 months ago
I think the answer is B) Planning with final assembly. It's the only one that says the production program won't be impacted if customers order more than the forecast.
upvoted 0 times
Elouise
10 days ago
A) Make-to-stock production (10) could work too, as long as there is enough buffer stock to cover unexpected customer orders.
upvoted 0 times
...
Jerry
13 days ago
I see your point, but D) Planning without final assembly (50) may not be the best option if customer orders exceed the forecast.
upvoted 0 times
...
Bobbie
17 days ago
I think C) Make-to-stock production (20) could also work, as it focuses on having the finished goods in stock.
upvoted 0 times
...
Loise
28 days ago
I agree, B) Planning with final assembly is the best choice.
upvoted 0 times
...
...
Bettina
2 months ago
I think the answer is A) Make-to-stock production.
upvoted 0 times
...

Save Cancel