You want to assign components to an equipment task list. There isno BOM assigned to the equipment. What is the prerequisite for using the free assignment of material?
I think the prerequisite for using the free assignment of material is to assign the header material of a material BOM to the equipment task list header.
Junita
7 months agoQuentin
6 months agoSherita
6 months agoQuinn
6 months agoNatalie
6 months agoAlita
6 months agoElenor
6 months agoHollis
7 months agoLashawna
7 months agoSantos
6 months agoBrandon
7 months agoKandis
7 months agoPura
7 months agoLatosha
7 months agoShoshana
7 months agoAshanti
7 months agoGlen
8 months agoDaniela
8 months agoRoxanne
7 months agoEllen
7 months agoFelton
8 months agoLouvenia
8 months agoYuriko
8 months agoGlen
8 months agoBecky
9 months agoMelissa
9 months agoKendra
7 months agoMozell
7 months agoOdette
7 months agoLucina
8 months agoValentine
9 months agoRaina
9 months agoLai
9 months agoGlen
9 months ago