SAP Exam C_TS412_2021 Topic 7 Question 37 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 37
Topic #: 7
[All C_TS412_2021 Questions]

You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Brock
6 months ago
Haha, I'm going to go with B and D. Who needs purchase orders and service milestones when you can just create activities in your network? That's the way to do it!
upvoted 0 times
Carmen
4 months ago
Yeah, I prefer keeping things simple by just creating external activities in the network.
upvoted 0 times
...
Arlean
5 months ago
I think having purchase orders and service milestones can add unnecessary complexity to the project.
upvoted 0 times
...
Erasmo
5 months ago
I agree, creating activities in the network seems like the most efficient way to handle external tasks.
upvoted 0 times
...
...
Lenna
6 months ago
I think creating a service milestone and activity might be considered external tasks in a project.
upvoted 0 times
...
Allene
6 months ago
I'm not sure, I think it could also be C and D.
upvoted 0 times
...
Shawn
6 months ago
I agree with Vi, assigning a purchase order and creating an external activity make sense.
upvoted 0 times
...
Vanesa
6 months ago
I agree with Alona. B and D are the right options. Assigning a purchase order and creating a service milestone don't seem to be the way to define an external task.
upvoted 0 times
...
Vi
6 months ago
I think the correct answers are A and B.
upvoted 0 times
...
Alona
6 months ago
B and D seem like the correct answers to me. Creating an external activity in a network and a service activity in a network are the ways to define an external task.
upvoted 0 times
Berry
6 months ago
So, B and D are the correct options for defining external tasks in a project.
upvoted 0 times
...
Coral
6 months ago
Assigning a purchase order and creating a service milestone are not ways to define external tasks.
upvoted 0 times
...
Jutta
6 months ago
Yes, creating an external activity in a network and a service activity in a network define external tasks.
upvoted 0 times
...
Peggie
6 months ago
I think B and D are the correct answers.
upvoted 0 times
...
Jerlene
6 months ago
Yes, creating an external activity in a network and a service activity in a network are the correct ways to define an external task.
upvoted 0 times
...
Jerlene
6 months ago
I agree, B and D are the correct answers. Those are the ways to define an external task.