Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 5 Question 43 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 43
Topic #: 5
[All C_TS412_2021 Questions]

Project Structures

Which the following statement regarding networks are correct?.

Note : there are 3 correct answers for this question.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Misty
21 days ago
Haha, this question is a real brain-teaser! I'm going with A, B, and D, but I'm still scratching my head on C. Maybe the system has a sense of humor and just reduces the capacity requirements as a joke?
upvoted 0 times
Avery
6 days ago
I think A, B, and D are correct. The system does propose alternative work centers.
upvoted 0 times
...
...
Paulene
28 days ago
The question is a bit tricky, but I believe A, B, and D are the right answers. E seems a bit questionable, as you can't assign the same work center to multiple activities on the same network.
upvoted 0 times
Rhea
1 days ago
I'm not sure about E either, but A, B, and D seem like the correct choices.
upvoted 0 times
...
Lanie
11 days ago
I agree, A, B, and D make sense. E does sound a bit strange.
upvoted 0 times
...
Sophia
19 days ago
I think you're right, A, B, and D are the correct answers. E does seem a bit off.
upvoted 0 times
...
...
Monte
2 months ago
I agree with Ruth, those statements make sense in terms of project structures.
upvoted 0 times
...
Hyman
2 months ago
I agree with Aracelis. B and D are definitely correct, and I think C is also true, as the capacity requirements should be reduced when the activity is confirmed.
upvoted 0 times
...
Aracelis
2 months ago
A, B, and D seem to be the correct answers. The system should be able to suggest alternative work centers if the capacity is exceeded.
upvoted 0 times
Wilda
7 days ago
D) During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
upvoted 0 times
...
Paulina
7 days ago
Yes, A, B, and D are correct. The system should be able to suggest alternative work centers if needed.
upvoted 0 times
...
Candra
28 days ago
B) You can assign more than one activity element to a network activity.
upvoted 0 times
...
Shawn
1 months ago
A) If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
upvoted 0 times
...
...
Ruth
2 months ago
I think the correct statements are A, B, and D.
upvoted 0 times
...

Save Cancel