BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 5 Question 43 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 43
Topic #: 5
[All C_TS412_2021 Questions]

Project Structures

Which the following statement regarding networks are correct?.

Note : there are 3 correct answers for this question.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Monte
15 days ago
I agree with Ruth, those statements make sense in terms of project structures.
upvoted 0 times
...
Hyman
18 days ago
I agree with Aracelis. B and D are definitely correct, and I think C is also true, as the capacity requirements should be reduced when the activity is confirmed.
upvoted 0 times
...
Aracelis
19 days ago
A, B, and D seem to be the correct answers. The system should be able to suggest alternative work centers if the capacity is exceeded.
upvoted 0 times
Shawn
4 days ago
A) If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
upvoted 0 times
...
...
Ruth
21 days ago
I think the correct statements are A, B, and D.
upvoted 0 times
...

Save Cancel