D) Availability control is the way to go. It's the only option that directly addresses the budget aspect of the question.
upvoted 0 times
...
Onita
20 days ago
Availability control? More like 'Availability out of control' if you ask me. Budgets are a nightmare!
upvoted 0 times
...
Wilson
21 days ago
B) Results analysis? Really? That's not even close to being about budget control. What were the question writers thinking?
upvoted 0 times
Myra
9 days ago
A) Easy cost planning is the correct budget function to check assigned values against the current budget.
upvoted 0 times
...
...
Doretha
22 days ago
D) Availability control is the obvious answer here. How else are you supposed to keep track of your budget?
upvoted 0 times
...
Rusty
26 days ago
C) Cost forecast sounds like the right choice to me. Forecasting costs is crucial for budget management.
upvoted 0 times
Lindsey
7 days ago
A) Easy cost planning is also important for tracking costs and staying within budget.
upvoted 0 times
...
...
Sharen
1 months ago
I think the correct answer is D) Availability control. It's the only option that specifically mentions checking assigned values against the current budget.
upvoted 0 times
Elliott
21 days ago
I agree, D) Availability control seems like the right choice for checking assigned values against the current budget.
upvoted 0 times
...
...
Lezlie
1 months ago
I'm not sure, but I think A) Easy cost planning could also be used for checking assigned values against the budget.
upvoted 0 times
...
Glory
1 months ago
I agree with Hannah, because Availability control is used to check assigned values against the current budget.
upvoted 0 times
...
Hannah
2 months ago
I think the answer is D) Availability control.