Haha, I'm just imagining the system automatically proposing a work center with a trampoline instead of a desk. 'Sorry, your spreadsheet tasks have exceeded the capacity of this cubicle, but we've found an alternative workspace in the gymnastics studio!'
I agree with Laura, C doesn't seem right. But I'm also a bit unsure about E - can you really assign the same work center to multiple activities on the same network? Seems like that could cause issues.
I think B and E are correct. We can assign more than one activity element to a network activity, and we can assign the same work center to more than one activity.
I think options B and E are definitely correct. You can definitely assign multiple activities to a network and the same work center to different activities.
Alyce
5 months agoFelix
4 months agoSophia
4 months agoDevora
5 months agoLeoma
4 months agoVicki
4 months agoIsabelle
4 months agoLaura
6 months agoCatrice
4 months agoAntonio
4 months agoJade
4 months agoNatalie
4 months agoLeota
4 months agoJaime
5 months agoCarolynn
6 months agoHildegarde
6 months agoAdelina
6 months agoBritt
6 months agoGail
7 months agoVirgie
7 months agoTresa
7 months agoThurman
7 months agoGerald
6 months agoWade
6 months agoGail
6 months agoThaddeus
7 months agoGregoria
7 months ago