The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Pamella
20 days ago
Unique for the entire project, huh? Sounds like a job for the controlling area. They're in charge of all that, right?
upvoted 0 times
Carlton
3 days ago
Actually, it's the company code that is unique for the entire project.
upvoted 0 times
...
Andrew
4 days ago
Yes, you're right! The controlling area is responsible for that.
upvoted 0 times
...
...
Nada
29 days ago
Plant? What is this, a gardening exam? I'm going to have to go with the company code on this one.
upvoted 0 times
Nenita
4 days ago
I agree, the company code is unique for the entire project.
upvoted 0 times
...
Nilsa
15 days ago
I think the correct answer is C) Company code.
upvoted 0 times
...
...
Cassie
1 months ago
I believe the correct answer is C) Company code because it identifies the company within the project.
upvoted 0 times
...
Lawrence
1 months ago
I'm not sure, but I think it might be B) Controlling area.
upvoted 0 times
...
Glen
1 months ago
I agree with Georgeanna, the company code is unique for the entire project.
upvoted 0 times
...
Rikki
2 months ago
The planning department? Really? That doesn't seem like it would be unique across the whole project. I'm going with C - Company code.
upvoted 0 times
...
Georgeanna
2 months ago
I think the correct answer is C) Company code.
upvoted 0 times
...
Kayleigh
2 months ago
Hmm, I think it might be the Controlling area. Sounds like the right kind of thing to be unique for a project.
upvoted 0 times
...
Fidelia
2 months ago
I'm pretty sure it's the Company code. That's the unique identifier for a project, right?
upvoted 0 times
Lorita
29 days ago
Actually, it's the Controlling area. That is unique for the entire project.
upvoted 0 times
...
Oliva
1 months ago
No, it's actually the Controlling area that is unique for the entire project.
upvoted 0 times
...
Leonida
1 months ago
I think it's the Controlling area. That's what distinguishes different projects.
upvoted 0 times
...
Pamella
1 months ago
Yes, you're correct. The Company code is the unique identifier for a project.
upvoted 0 times
...
Magdalene
1 months ago
Yes, you're correct. The Company code is the unique identifier for a project.
upvoted 0 times
...
...