Which statement regarding the creation of a new work breakdown structure (WBS element) are true?

Note : there are 3 correct answer for this question.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Ahmed
5 months ago
I'm chuckling at the 10-level limit. Clearly, the person who wrote this has never worked on a construction project. A, D, and E are the way to go.
upvoted 0 times
Carin
4 months ago
Absolutely, having the ability to assign WBS elements to different project definitions is crucial for project management. A, D, and E are definitely true.
upvoted 0 times
...
Erasmo
4 months ago
Yes, I think A, D, and E are the correct statements. It makes sense to have flexibility in creating WBS elements.
upvoted 0 times
...
Inocencia
4 months ago
It's important to have flexibility in creating WBS elements.
upvoted 0 times
...
Lajuana
4 months ago
I agree, the 10-level limit seems unrealistic. A new WBS can definitely have multiple levels.
upvoted 0 times
...
Bette
4 months ago
Definitely, A, D, and E are the correct statements.
upvoted 0 times
...
Evan
5 months ago
I agree, the 10-level limit seems unrealistic.
upvoted 0 times
...
...
Celeste
5 months ago
I agree with both of you. Statement C is also true as it allows for cross-project assignment.
upvoted 0 times
...
Kattie
5 months ago
I disagree, I believe statement E is true because it mentions multiple level 1 WBS elements.
upvoted 0 times
...
Michal
5 months ago
I think statement A is true because it allows for flexibility in structuring the project.
upvoted 0 times
...
Jeannetta
5 months ago
I'm going with A, D, and E. Who comes up with these silly rules about WBS structure? As long as it works for the project, that's what matters.
upvoted 0 times
...
Jesus
5 months ago
I think option E is true too, as the WBS structure can have several level 1 elements for organization.
upvoted 0 times
...
Buddy
5 months ago
Ha! 10 levels, really? Clearly the person who wrote this question has never managed a complex project. A, D, and E are spot on.
upvoted 0 times
Rikki
4 months ago
E) The WBS structure can contain several level 1 WBS element
upvoted 0 times
...
Nicholle
4 months ago
A, D, and E are definitely true.
upvoted 0 times
...
Ashton
4 months ago
D) WBS element can be a planning element, an account assignment element, and a billing element at the same time.
upvoted 0 times
...
Matt
5 months ago
User 2
upvoted 0 times
...
Vanna
5 months ago
User 1
upvoted 0 times
...
Florinda
5 months ago
A) You can create several WBS elements per level.
upvoted 0 times
...
...
Tamar
5 months ago
Yes, that's a good point. It helps with project flexibility.
upvoted 0 times
...
Avery
6 months ago
Definitely agree with A, D, and E. The WBS is supposed to be flexible and tailored to the project's needs. Limiting it to 10 levels is just arbitrary.
upvoted 0 times
Vivan
5 months ago
Yeah, limiting it to 10 levels doesn't seem practical. A, D, and E cover the important aspects.
upvoted 0 times
...
Hollis
5 months ago
I agree, A, D, and E make sense for a flexible WBS structure.
upvoted 0 times
...
...
Dorthy
6 months ago
A, D, and E seem like the correct options here. Multiple WBS elements per level and having elements serve multiple purposes are common practices.
upvoted 0 times
Yuki
5 months ago
E) The WBS structure can contain several level 1 WBS element
upvoted 0 times
...
Nida
5 months ago
D) WBS element can be a planning element, an account assignment element, and a billing element at the same time.
upvoted 0 times
...
Cristina
5 months ago
Yes, I agree. It allows for more detailed planning and organization.
upvoted 0 times
...
Peggie
5 months ago
I think A, D, and E are correct. It makes sense to have multiple WBS elements per level.
upvoted 0 times
...
Gladys
6 months ago
A) You can create several WBS elements per level.
upvoted 0 times
...
...
Jovita
6 months ago
I believe option C is also true because WBS elements can be assigned to different project definitions.
upvoted 0 times
...
Angella
6 months ago
I agree with Tamar, that makes sense for project organization.
upvoted 0 times
...
Tamar
6 months ago
I think option A is true because we can create multiple WBS elements per level.
upvoted 0 times
...

Save Cancel