SAP Exam C_TS412_2021 Topic 3 Question 22 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 22
Topic #: 3
[All C_TS412_2021 Questions]

Materials

Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set

of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, E

In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:

Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.

Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html


Contribute your Thoughts:

Micaela
5 months ago
Yeah, those two seem like the most logical options based on the requirements of the project system.
upvoted 0 times
...
Glennis
5 months ago
Did someone say 'scheduling'? I'm on it! A) Planned dates and D) Baseline dates are the way to go. Though I'm tempted to throw in a wild card like C) Basic dates just to keep the professor on their toes.
upvoted 0 times
Irving
4 months ago
Let's stick with the safe choices of A) Planned dates and D) Baseline dates for scheduling.
upvoted 0 times
...
Cecilia
4 months ago
I think C) Basic dates could also be a good option to consider, just to cover all bases.
upvoted 0 times
...
Lorrie
4 months ago
I agree, A) Planned dates and D) Baseline dates are the best choices for scheduling.
upvoted 0 times
...
...
Alba
5 months ago
I'm not sure about Fundamental, Basic, or Forecast dates, but I think Planned and Baseline dates are commonly used for scheduling tasks.
upvoted 0 times
...
Ettie
5 months ago
I agree with Micaela, Planned dates and Baseline dates make sense for scheduling in the network.
upvoted 0 times
...
Jesusa
6 months ago
This is easy! A) Planned dates and D) Baseline dates for sure. I mean, why would they even ask about 'basic' or 'forecast' dates? That's just silly.
upvoted 0 times
...
Elenore
6 months ago
I'm going with B) Fundamental dates and E) Forecast dates. Gotta think outside the box, you know? Who needs 'planned' dates when you can have 'fundamental' ones?
upvoted 0 times
Luke
5 months ago
I agree with you, I also chose B) Fundamental dates and E) Forecast dates.
upvoted 0 times
...
Stacey
5 months ago
I think A) Planned dates and C) Basic dates are the correct options.
upvoted 0 times
...
...
Micaela
6 months ago
I think the correct answers are A) Planned dates and D) Baseline dates.
upvoted 0 times
...
Rikki
6 months ago
Hmm, I think the answer is A) Planned dates and D) Baseline dates. Those seem to be the most relevant for scheduling networks in the project system.
upvoted 0 times
Lizbeth
5 months ago
Yes, those are the dates that are commonly used for specifying planned dates of tasks in the project system.
upvoted 0 times
...
Stefania
5 months ago
I agree, A) Planned dates and D) Baseline dates are the correct options for scheduling networks.
upvoted 0 times
...
...
Lauryn
6 months ago
I don't think Fundamental dates would be used for scheduling network tasks. It seems more like Planned dates and Baseline dates would be the ones.
upvoted 0 times
...
Ruth
6 months ago
I'm not sure about Fundamental dates. Does anyone think that could be one of the correct answers?
upvoted 0 times
...
Martina
6 months ago
I agree with you, Franchesca. Planned dates and Baseline dates make the most sense for scheduling network tasks.
upvoted 0 times
...
Franchesca
6 months ago
I think the correct answers are A) Planned dates and D) Baseline dates.
upvoted 0 times
...