Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set
of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
Micaela
5 months agoGlennis
5 months agoIrving
4 months agoCecilia
4 months agoLorrie
4 months agoAlba
5 months agoEttie
5 months agoJesusa
6 months agoElenore
6 months agoLuke
5 months agoStacey
5 months agoMicaela
6 months agoRikki
6 months agoLizbeth
5 months agoStefania
5 months agoLauryn
6 months agoRuth
6 months agoMartina
6 months agoFranchesca
6 months ago