Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_2021 Topic 2 Question 48 Discussion

Actual exam question for SAP's C_TS412_2021 exam
Question #: 48
Topic #: 2
[All C_TS412_2021 Questions]

You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?

Note : there are 2 correct answers for this question.

Show Suggested Answer Hide Answer

Contribute your Thoughts:

Refugia
12 days ago
Hmm, B and C seem like they might work, but I'm not sure they're the most efficient options. A and D get my vote.
upvoted 0 times
Freeman
1 days ago
I agree, D could also work well if you calculate the start date accurately.
upvoted 0 times
...
Tora
5 days ago
I think A is the way to go, it's the most straightforward option.
upvoted 0 times
...
...
Lashon
27 days ago
Wait, we're supposed to plan activities around a network, material, and milestones? That sounds like a lot of moving parts. I'll go with A and D just to keep things simple.
upvoted 0 times
Maryann
18 days ago
User 2: I agree. I think using an offset of two days for the relationship of both activities and setting constraints can help.
upvoted 0 times
...
Dominic
19 days ago
User 1: Planning activities around network, material, and milestones can be complex.
upvoted 0 times
...
...
Catalina
1 months ago
I'm not sure, I think option B) could also be correct because milestone dates are important in project planning
upvoted 0 times
...
Sylvie
1 months ago
Haha, trying to trick us with two correct answers? I'm on to you! But seriously, I agree with A and D.
upvoted 0 times
...
Alfred
1 months ago
I think the correct answers are A and D. Using an offset of two days for the relationship and setting a constraint on the start date makes the most sense to me.
upvoted 0 times
Truman
4 days ago
I think the correct answers are A and D.
upvoted 0 times
...
...
Effie
1 months ago
I agree with Ailene, setting an offset for the relationship and calculating the start date seem like the right approach
upvoted 0 times
...
Ailene
1 months ago
I think the correct answers are A) and D)
upvoted 0 times
...

Save Cancel