Cost and Budget
What function are available for period end-closing in the project System?
Period-end closing is a process that involves various activities to finalize the project costs and revenues at the end of a period. Some of the functions that are available for period-end closing in the Project System are:
Result analysis: This function allows you to calculate the work in process (WIP), reserves, and results for a project based on various methods and valuation rules. Result analysis also updates the financial accounting (FI) and controlling (CO) documents with the calculated values.
Progress analysis: This function allows you to measure and monitor the progress of a project based on various criteria, such as costs, revenues, dates, or quantities. Progress analysis also enables you to compare the planned and actual progress of a project and identify any deviations or delays.
Settlement: This function allows you to transfer the costs and revenues of a project to one or more receivers, such as cost centers, fixed assets, profitability segments, or sales orders. Settlement also clears the balances of the project objects and updates the corresponding accounting documents. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
Gregoria
2 months agoMaryann
2 months agoBeckie
1 months agoSage
1 months agoSerina
1 months agoShawna
2 months agoUlysses
1 months agoRosita
2 months agoMari
2 months agoDona
2 months agoKizzy
2 months agoMarti
3 months agoOdette
3 months agoLemuel
2 months agoGlen
2 months agoCaitlin
2 months agoWinfred
2 months ago