BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TS412_1909 Topic 1 Question 13 Discussion

Actual exam question for SAP's C_TS412_1909 exam
Question #: 13
Topic #: 1
[All C_TS412_1909 Questions]

Materials

Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set

of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.

Show Suggested Answer Hide Answer
Suggested Answer: C, E

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel