BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TPLM22_67 Topic 2 Question 20 Discussion

Actual exam question for SAP's C_TPLM22_67 exam
Question #: 20
Topic #: 2
[All C_TPLM22_67 Questions]

Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned?

There are 3 correct answers to this question.

Response:

Show Suggested Answer Hide Answer
Suggested Answer: A, B, D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel