Question #: 25
Topic #: 5
[All C_TFG51_2211 Questions]

You need to create a Corporate Calendar that allows for regional differences in standard work schedules. What details can the Corporate Calendar include? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, D

Contribute your Thoughts:

Marjory
3 months ago
A and D, hands down. Gotta keep track of those regional holidays, am I right? Although, a good calendar should also include the mandatory company picnic. Can't forget that!
upvoted 0 times
...
Florinda
3 months ago
On-boarding and off-boarding activities? Seriously? That's HR's job, not the Corporate Calendar's.
upvoted 0 times
Darell
2 months ago
C) Core hours when workers are expected to be in the office, or on-site
upvoted 0 times
...
Darell
2 months ago
A) Specific non-working days
upvoted 0 times
...
...
Levi
3 months ago
Core hours are a must! How else will we know when to schedule all those pointless meetings?
upvoted 0 times
Carrol
1 months ago
B) On-boarding and off-boarding activities
upvoted 0 times
...
Lourdes
2 months ago
Yes, core hours are essential for scheduling meetings efficiently.
upvoted 0 times
...
Rebbecca
2 months ago
C) Core hours when workers are expected to be in the office, or on-site
upvoted 0 times
...
Elly
2 months ago
A) Specific non-working days
upvoted 0 times
...
...
Twana
3 months ago
I think core hours when workers are expected to be in the office should also be included for better coordination.
upvoted 0 times
...
Georgene
3 months ago
I believe on-boarding and off-boarding activities should be included as well.
upvoted 0 times
...
Mattie
3 months ago
I agree with Mitsue, it should also include recurring non-working days.
upvoted 0 times
...
Rashad
4 months ago
I think the Corporate Calendar should definitely include specific non-working days and recurring non-working days. That way everyone is on the same page about when the office is closed.
upvoted 0 times
Polly
3 months ago
C) Core hours when workers are expected to be in the office, or on-site
upvoted 0 times
...
Mary
3 months ago
D) Recurring non-working days
upvoted 0 times
...
Myra
3 months ago
A) Specific non-working days
upvoted 0 times
...
...
Mitsue
4 months ago
I think the Corporate Calendar can include specific non-working days.
upvoted 0 times
...

Save Cancel