BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

SAP Exam C_TERP10_67 Topic 10 Question 57 Discussion

Actual exam question for SAP's C_TERP10_67 exam
Question #: 57
Topic #: 10
[All C_TERP10_67 Questions]

In Project System, which of the following operative indicators can you set in a WBS element?

There are 3 correct answers to this question.

Response:

Show Suggested Answer Hide Answer
Suggested Answer: A, B, E

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel