What do you have to consider when planning maintenance work that is to be carried out by an external company?
When planning maintenance work that is to be carried out by an external company, you have to consider the following aspects:
If you assign a control key with indicator ''Service'' for an external service, you have to enter the actual values via the service entry sheet. This is because the service entry sheet is used to record the services performed by the external company and to verify the invoice. The service entry sheet is linked to the purchase order and the maintenance order operation.
For the maintenance order type, you have to assign the Enhanced Procurement Mode. This is because the Enhanced Procurement Mode enables you to use lean services and enhanced limits for external services. Lean services are intended for the procurement of small or highly specialized services that are carried out by external suppliers as part of an internal or external operation. They can be maintained in the material master as service products. Enhanced limits allow you to define a maximum amount for the external service without specifying the service specifications in advance.
If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system. This is not true, because the goods receipt is only required for external materials, not for external services. For external services, the service entry sheet is used instead.
Anglea
1 months agoLevi
1 months agoVincenza
15 days agoRosalyn
18 days agoNell
20 days agoWilliam
1 months agoRoslyn
4 days agoFernanda
11 days agoCamellia
15 days agoAliza
19 days agoDeandrea
2 months agoBambi
2 months agoTammi
13 days agoLeonora
14 days agoNoah
22 days agoMireya
2 months agoKenneth
2 months agoMabelle
16 days agoRory
25 days agoThaddeus
1 months agoCarissa
1 months agoDeandrea
2 months agoLarae
2 months ago