You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time-key date. The orders should be called 3 months before the planned date.How can you set up the maintenance plan? Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B, D

A notification item is used to describe a problem, damage, or the activity executed in greater detail. A notification item can be assigned to one or more object parts and one or more causes of damage. An object part is a component of a technical object that is affected by a malfunction or damage. A cause of damage is a factor that leads to a malfunction or damage. You can use catalogs to enter object parts and causes of damage in a coded form. Therefore, the correct answers are B and D.

References:

SAP Help Portal - Notification Item

SAP Help Portal - Object Part

SAP Help Portal - Cause of Damage

[SAP Learning - Creating Notifications]


Contribute your Thoughts:

Billy
3 days ago
I disagree, I believe we should set the offset to 3 months.
upvoted 0 times
...
Cheryl
4 days ago
I think we should set the call horizon to 75%.
upvoted 0 times
...