SAP Exam C_S43_2022 Topic 1 Question 10 Discussion

Actual exam question for SAP's C_S43_2022 exam
Question #: 10
Topic #: 1
[All C_S43_2022 Questions]

You want to assign components to a General Maintenance Task List. What are prerequisites for assigning material components to a task list operation? Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B, D

To assign material components to a task list operation, you need to meet the following prerequisites:

You need to assign the BOM usage for free assignment of material in Customizing. This allows you to assign any material BOM to a task list operation, regardless of the assembly. This is option B in the question.

You need to assign a piece of equipment with allocated material BOM to a task list operation. This allows you to use the material BOM of the equipment as a source of components for the task list operation. This is option D in the question.

Option A is incorrect because you cannot assign the header material of a material BOM as assembly to a task list operation. You can only assign the header material of a material BOM to the assembly field of the task list header.

Option C is incorrect because you cannot assign the header material of a material ROM to the assembly field of the task list header. A material ROM is a routing-oriented material, which is used for production orders, not for maintenance task lists.


Process Task List | SAP Help Portal

Processing Maintenance Orders - SAP Learning

Contribute your Thoughts:

Sherman
4 months ago
That makes sense. And what about assigning a piece of equipment with allocated material BOM to a task list operation?
upvoted 0 times
...
Daniel
4 months ago
I believe we also need to assign the header material of a material ROM to the assembly field of the task list header.
upvoted 0 times
...
Gladys
4 months ago
I agree, that could be one of the prerequisites. But what about assigning the BOM usage for free assignment of material in Customizing?
upvoted 0 times
...
Ashley
5 months ago
I think we need to assign the header material of a material BOM as assembly to a task list operation.
upvoted 0 times
...
Solange
5 months ago
I think we can also assign the header material of a material ROM to the assembly field of the task list header as another prerequisite. That makes sense to me.
upvoted 0 times
...
Tori
5 months ago
That's a good point, Mindy. It seems like there are multiple correct answers for this question. We need to consider all the options carefully.
upvoted 0 times
...
Noel
5 months ago
I'm with Lilli on this one. D is just a bizarre option. It's like they're trying to trick us or something.
upvoted 0 times
Frank
5 months ago
B) Assign the BOM usage for free assignment of material in Customizing
upvoted 0 times
...
Kimberlie
5 months ago
A) Assign the header material of a material BOM as assembly to a task list operation.
upvoted 0 times
...
Ollie
5 months ago
B) Assign the BOM usage for free assignment of material in Customizing
upvoted 0 times
...
Shad
5 months ago
A) Assign the header material of a material BOM as assembly to a task list operation.
upvoted 0 times
...
...
Lilli
5 months ago
D is just silly. Assigning a piece of equipment with an allocated material BOM to a task list operation? That's like trying to put a square peg in a round hole!
upvoted 0 times
Dulce
4 months ago
B) Assign the BOM usage for free assignment of material in Customizing
upvoted 0 times
...
Jani
5 months ago
A) Assign the header material of a material BOM as assembly to a task list operation.
upvoted 0 times
...
Talia
5 months ago
B) Assign the BOM usage for free assignment of material in Customizing
upvoted 0 times
...
Talia
5 months ago
A) Assign the header material of a material BOM as assembly to a task list operation.
upvoted 0 times
...
...
Mindy
6 months ago
I'm not sure about that. I think we also need to assign the BOM usage for free assignment of material in Customizing. That's one of the correct answers.
upvoted 0 times
...
Alesia
6 months ago
I think C is also a correct answer. Assigning the header material of a material ROM to the assembly field of the task list header should work too.
upvoted 0 times
Andra
5 months ago
B) Assign the BOM usage for free assignment of material in Customizing
upvoted 0 times
...
Andra
6 months ago
A) Assign the header material of a material BOM as assembly to a task list operation.
upvoted 0 times
...
...
Dominga
6 months ago
A and B are the correct answers. You need to assign the header material of a material BOM as the assembly, and also enable the BOM usage for free assignment of material in Customizing.
upvoted 0 times
Lashawn
5 months ago
B) Assign the BOM usage for free assignment of material in Customizing.
upvoted 0 times
...
Queenie
5 months ago
A) Assign the header material of a material BOM as assembly to a task list operation.
upvoted 0 times
...
...
Josue
6 months ago
Yes, I agree with you, Tori. I also believe that assigning a piece of equipment with allocated material BOM to a task list operation is another prerequisite.
upvoted 0 times
...
Tori
6 months ago
I think the prerequisites for assigning material components to a task list operation include assigning the header material of a material BOM as assembly, don't you think so?
upvoted 0 times
...

Save Cancel