You want to assign components to a General Maintenance Task List. What are prerequisites for assigning material components to a task list operation? Note: There are 2 correct answers to this question
To assign material components to a task list operation, you need to meet the following prerequisites:
You need to assign the BOM usage for free assignment of material in Customizing. This allows you to assign any material BOM to a task list operation, regardless of the assembly. This is option B in the question.
You need to assign a piece of equipment with allocated material BOM to a task list operation. This allows you to use the material BOM of the equipment as a source of components for the task list operation. This is option D in the question.
Option A is incorrect because you cannot assign the header material of a material BOM as assembly to a task list operation. You can only assign the header material of a material BOM to the assembly field of the task list header.
Option C is incorrect because you cannot assign the header material of a material ROM to the assembly field of the task list header. A material ROM is a routing-oriented material, which is used for production orders, not for maintenance task lists.
Sherman
1 years agoDaniel
1 years agoGladys
1 years agoAshley
1 years agoSolange
1 years agoTori
1 years agoNoel
1 years agoFrank
1 years agoKimberlie
1 years agoOllie
1 years agoShad
1 years agoLilli
1 years agoDulce
1 years agoJani
1 years agoTalia
1 years agoTalia
1 years agoMindy
1 years agoAlesia
1 years agoAndra
1 years agoAndra
1 years agoDominga
1 years agoLashawn
1 years agoQueenie
1 years agoJosue
1 years agoTori
1 years ago