An employee's time recording method is set to "POSITIVE". The employee is assigned a clock-time based work.

schedule. The working hours are defined to be from 8:00 to 17:00.

The employee is also assigned to a working time account, where planned working hours are capped.

The employee records two time entries for a particular day.

The first is from 9:00 to 15:00, and the second entry is from 17 :00 to 21 :00.

What is the posting quantity for this date in the working time account?

Show Suggested Answer Hide Answer
Suggested Answer: A