Question #: 19
Topic #: 9
[All C_ARCON_2404 Questions]

Procurement Knowledge

When does a published contract have a Pending contract status?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Kassandra
5 days ago
I'm going with B. Who doesn't love a good ol' fashioned contract approval process?
upvoted 0 times
...
Aja
20 days ago
Haha, I bet the procurement team is just waiting for the ink to dry on these contracts before they can move them to the next status!
upvoted 0 times
Lisha
12 days ago
A) The effective date is in the future
upvoted 0 times
...
...
Camellia
28 days ago
I agree with Nan, if the tasks are not completed, the contract may still be pending
upvoted 0 times
...
Cherelle
1 months ago
D seems like the right answer to me. The agreement date being in the future would definitely put the contract in a Pending status.
upvoted 0 times
Jeniffer
5 days ago
So, the contract status would change once the agreement date is reached?
upvoted 0 times
...
Shanda
18 days ago
Yes, I agree. If the agreement date hasn't passed yet, the contract would be pending.
upvoted 0 times
...
Naomi
19 days ago
I think D is correct, the agreement date being in the future makes sense.
upvoted 0 times
...
...
Nan
1 months ago
I think it could also be C) The required tasks have not been completed
upvoted 0 times
...
Jamika
1 months ago
Hmm, I'm not so sure. What if the effective date is in the future? Wouldn't that also be a valid Pending status?
upvoted 0 times
Cary
2 days ago
User 3: C) The required tasks have not been completed
upvoted 0 times
...
Viki
6 days ago
User 2: B) The contract documents need approval
upvoted 0 times
...
Sommer
9 days ago
User 1: A) The effective date is in the future
upvoted 0 times
...
...
Corinne
1 months ago
A) The effective date is in the future
upvoted 0 times
...
Nell
1 months ago
I think the answer is B. The contract documents need approval before the contract can have a Pending status.
upvoted 0 times
Avery
28 days ago
Yes, that's correct. The contract status will remain Pending until all documents are approved.
upvoted 0 times
...
Heidy
1 months ago
I agree, the contract documents need approval before it can have a Pending status.
upvoted 0 times
...
...

Save Cancel