Which of the following are SAP Activate workstreams?Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: B, D

B is correct because Project Management is one of the SAP Activate workstreams. The Project Management workstream covers all the activities related to planning, executing, monitoring, controlling, and closing the project. It includes tasks such as defining project scope, schedule, budget, resources, risks, issues, quality, communication, and stakeholder management.

D is correct because Data Migration is one of the SAP Activate workstreams. The Data Migration workstream covers all the activities related to preparing, extracting, transforming, validating, and loading data from legacy systems to SAP systems. It includes tasks such as defining data migration strategy, scope, approach, tools, roles, responsibilities, quality criteria, and testing scenarios. Verified Reference:

:SAP Activate Methodology Workstreams Names update

:SAP Activate Testing Workstream


Contribute your Thoughts:

Dottie
30 days ago
I almost went with Extensibility for a second there. Glad I double-checked the materials. Change Management and Project Management are the clear winners here. Now, if only the rest of the exam was this straightforward...
upvoted 0 times
Whitney
7 days ago
I agree, Change Management and Project Management are the correct SAP Activate workstreams.
upvoted 0 times
...
...
Olive
1 months ago
Haha, Extensibility and Data Migration? What is this, a trick question? I'm glad I studied the SAP Activate framework thoroughly. Change Management and Project Management for the win!
upvoted 0 times
Annamae
5 days ago
Extensibility and Data Migration are also important workstreams in SAP Activate, don't underestimate them.
upvoted 0 times
...
Kristeen
5 days ago
I know, right? Change Management and Project Management are key workstreams in SAP Activate.
upvoted 0 times
...
...
Raina
1 months ago
C'mon, Extensibility and Data Migration? Really? Those are like, totally separate topics. I'm with Charolette on this one - the right answers are A and B.
upvoted 0 times
Dierdre
14 days ago
Maybe, but I still believe Change Management and Project Management are the main workstreams.
upvoted 0 times
...
Glenn
27 days ago
But don't you think Extensibility and Data Migration are important aspects of SAP Activate?
upvoted 0 times
...
Nikita
29 days ago
No way, I agree with Charolette, Change Management and Project Management are the correct ones.
upvoted 0 times
...
Caren
1 months ago
I think Extensibility and Data Migration are part of SAP Activate workstreams.
upvoted 0 times
...
...
Delila
2 months ago
Yep, Change Management and Project Management are the correct answers here. I wonder if they'll ask us to name all 5 workstreams in the next question? *fingers crossed*
upvoted 0 times
Linn
26 days ago
B) Project Management
upvoted 0 times
...
Rodrigo
27 days ago
A) Change Management
upvoted 0 times
...
...
Audria
2 months ago
I'm not sure about Extensibility and Data Migration. I think they are not part of SAP Activate workstreams.
upvoted 0 times
...
Jesus
2 months ago
I agree with Holley. Those workstreams are crucial for SAP Activate.
upvoted 0 times
...
Charolette
2 months ago
Change Management and Project Management are definitely two of the SAP Activate workstreams. The other two options are a bit too specific, in my opinion.
upvoted 0 times
Alpha
30 days ago
It's good to have a mix of perspectives on which workstreams are essential for SAP Activate.
upvoted 0 times
...
Delpha
1 months ago
I see your point, but I think Extensibility and Data Migration are more specialized workstreams.
upvoted 0 times
...
Thaddeus
2 months ago
Extensibility and Data Migration are important too, they play a crucial role in the implementation process.
upvoted 0 times
...
Scarlet
2 months ago
I agree, Change Management and Project Management are key workstreams.
upvoted 0 times
...
...
Holley
2 months ago
I think the correct answers are A) Change Management and B) Project Management.
upvoted 0 times
...

Save Cancel