MultipleChoice
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.
OptionsMultipleChoice
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
OptionsMultipleChoice
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
OptionsMultipleChoice
The individual tasks in the project are mapped as activities in a WBS. Determine whether this statement is true or false.
OptionsMultipleChoice
Cost & Budget
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation.,
and have entered the quotation ...
What is the typical sequence for the following business transactions and document.
OptionsMultipleChoice
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
OptionsMultipleChoice
Dates
You want to exchange data between SAP Project System and Microsoft What interface do you use?
OptionsMultipleChoice
Project Structure
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note : there are 3 correct answer for this question.
Options