New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Salesforce Exam Business Analyst Topic 5 Question 15 Discussion

Actual exam question for Salesforce's Business Analyst exam
Question #: 15
Topic #: 5
[All Business Analyst Questions]

Northern Trail Outfitters is undergoing a service Cloud implementation and has decided to use the Scrum methodology for the implementation. A business analyst (BA) received an urgent, high-priority change request in the middle of a sprint.

Which step should the BA take next?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Chandrasekhar
2 years ago
I feel option A is wrong because option A belongs to Kanban methodology
upvoted 2 times
...
Jackpot
2 years ago
The scope is locked once the sprint starts. I thought it should be option B (adding it to the next Sprint)?
upvoted 2 times
...

Save Cancel