New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Salesforce Exam Business Analyst Topic 10 Question 17 Discussion

Actual exam question for Salesforce's Business Analyst exam
Question #: 17
Topic #: 10
[All Business Analyst Questions]

Northern Trail Outfitters is undergoing a service Cloud implementation and has decided to use the Scrum methodology for the implementation. A business analyst (BA) received an urgent, high-priority change request in the middle of a sprint.

Which step should the BA take next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Sulpice
2 years ago
are you sure about answer C ? we can't make change in middle of a sprint
upvoted 2 times
...

Save Cancel