New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Salesforce Exam ANC-301 Topic 1 Question 21 Discussion

Actual exam question for Salesforce's ANC-301 exam
Question #: 21
Topic #: 1
[All ANC-301 Questions]

The Tableau CRM team at a company creates three recipes.

1) myRecipeOne: this recipe takes 2 hours to run.

2) mvRedpeTwo: this recipe takes 1 hour and 30 minutes to run.

3) myRecipeThree: this recipe takes 1 minute and 30

seconds to run.

If all three recipes run, how many count towards the 24 hour rolling recipe run limit.

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel