New Year Sale ! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 4 Question 80 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 80
Topic #: 4
[All PRINCE2-Practitioner Questions]

MANAGING PRODUCT DELIVERY

Stage 2 is in progress. While producing the team plan, the team manager responsible for the work package to develop the 'classroom-based training material' discovered that the representatives assigned to check the products were unsuitable.

Which action should the team manager take in response?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Keshia
2 days ago
D. Raising an exception report seems like the most logical choice here. The team manager needs to escalate this issue to the project manager to ensure it's addressed properly.
upvoted 0 times
...
Rebbecca
4 days ago
I agree with Rose. It's important to get guidance from project assurance in such cases.
upvoted 0 times
...
Rose
10 days ago
I think the team manager should discuss the situation with project assurance.
upvoted 0 times
...
Adelle
12 days ago
I think the correct answer is B. Advising the project manager of this risk is the appropriate action to take, as they need to be informed of any issues that could impact the project.
upvoted 0 times
...

Save Cancel