Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 4 Question 69 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 69
Topic #: 4
[All PRINCE2-Practitioner Questions]

The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.

Is this an appropriate action, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Sanjuana
7 days ago
Haha, maybe the supplier got stuck in traffic on their way to send the report. Either way, the project manager needs to crack the whip and get that report ASAP!
upvoted 0 times
...
Herschel
9 days ago
Option D seems too passive. The project manager shouldn't just discuss the plan with the supplier. They need to take action to get the report on time.
upvoted 0 times
...
Francoise
12 days ago
I don't think option C is the right approach. The project manager shouldn't be checking interfaces first when a critical report is missing.
upvoted 0 times
Berry
3 days ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Lorrie
17 days ago
I agree, we need to ensure all deliverables are on time to meet project deadlines.
upvoted 0 times
...
Pilar
22 days ago
I agree with option B. With zero time tolerance, the checkpoint report must be on time. The project manager needs to address this delay immediately.
upvoted 0 times
Helene
11 days ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Dana
30 days ago
I think raising an exception report is necessary to address the late checkpoint report.
upvoted 0 times
...
Margarita
1 months ago
Yes, option A is the correct answer. The project manager should raise an exception report to get guidance on how to handle this situation. Waiting for the late report could jeopardize the entire project timeline.
upvoted 0 times
Carolynn
23 days ago
The project manager should raise an exception report to get guidance on how to handle this situation.
upvoted 0 times
...
Yoko
25 days ago
Yes, option A is the correct answer.
upvoted 0 times
...
...
Jimmie
1 months ago
C) No, because the project manager should check the operations and maintenance interfaces in the work package first.
upvoted 0 times
...
Lorrie
1 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Dana
1 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...

Save Cancel