BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 4 Question 64 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 64
Topic #: 4
[All PRINCE2-Practitioner Questions]

The project is in stage 3. Zero time tolerance has been given for this stage. When checking progress, the project manager noticed that the checkpoint report from the external supplier of the 'e-learning course' is late. As work package progress information is missing, the project manager has decided to raise an exception report.

Is this an appropriate action, and why?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Von
5 months ago
Honestly, this question is making my head hurt. I'm just going to go with option A and hope for the best. Raising an exception report seems like the safest bet.
upvoted 0 times
...
Kasandra
5 months ago
Ha! I bet the project manager is just looking for an excuse to write up a long and dramatic exception report. Option D is the way to go - discuss the team plan with the supplier first.
upvoted 0 times
Crista
4 months ago
Yeah, I agree. It's important to communicate and see if the work can still be completed on time.
upvoted 0 times
...
Dominga
4 months ago
Option D is better, discussing the team plan with the supplier seems more reasonable.
upvoted 0 times
...
Chaya
4 months ago
The project manager is just trying to make a big deal out of this.
upvoted 0 times
...
...
Nada
5 months ago
I'm not sure I agree. Option C seems like a better approach - the project manager should check the operations and maintenance interfaces first before raising an exception report.
upvoted 0 times
...
Christiane
5 months ago
Option B makes the most sense to me. Since there is zero time tolerance for this stage, the checkpoint report must be delivered on time, so an exception report is appropriate.
upvoted 0 times
Weldon
4 months ago
Option B makes the most sense to me. Since there is zero time tolerance for this stage, the checkpoint report must be delivered on time, so an exception report is appropriate.
upvoted 0 times
...
Veda
4 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Doretha
4 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...
Bette
5 months ago
I think option A is the correct answer. The project manager should raise an exception report to get guidance on how to handle the late checkpoint report from the external supplier.
upvoted 0 times
Gracie
4 months ago
A) I agree, the project manager needs guidance on how to handle the situation.
upvoted 0 times
...
Lai
5 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Rene
5 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Maurine
5 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
Jarvis
5 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Salome
5 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
Leota
5 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
Angelo
5 months ago
B) Yes, because there is zero time tolerance for this stage the checkpoint report must be delivered on time.
upvoted 0 times
...
Leslie
5 months ago
A) Yes, because an exception report should be used to request guidance on how this situation should be handled.
upvoted 0 times
...
...

Save Cancel