BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 4 Question 59 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 59
Topic #: 4
[All PRINCE2-Practitioner Questions]

The project is part of a program to increase the number of ABC courses that respond to legislation. The program manager has instructed the project manager to deliver the 'e-learning course' incrementally. The project manager has asked the program manager how often the highlight reports are required, and what format the reports should be presented in.

Is this an appropriate approach to controlling progress, and why?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Glen
4 months ago
I think it's key for the project manager to communicate with the program manager to ensure alignment and successful delivery.
upvoted 0 times
...
Nettie
4 months ago
I agree, having frequent progress updates can help ensure that the project stays on track and meets its objectives.
upvoted 0 times
...
Willodean
4 months ago
I believe that regular highlight reports are crucial for tracking progress and making adjustments as needed.
upvoted 0 times
...
Mabelle
4 months ago
Agreed, it's important for the project manager to align with the overall program goals.
upvoted 0 times
...
Carlton
5 months ago
I think the project manager should follow the instructions given by the program manager.
upvoted 0 times
...
Dottie
5 months ago
I see your point, but having clear documentation from the beginning might prevent any confusion later on.
upvoted 0 times
...
Rebeca
5 months ago
But wouldn't aligning project controls with program controls help in overall coordination?
upvoted 0 times
...
Rory
6 months ago
I disagree, I believe option D is better to document progress controls clearly from the start.
upvoted 0 times
...
Dottie
6 months ago
I agree with Candidate A, option B ensures that progress is monitored effectively.
upvoted 0 times
...
Rebeca
6 months ago
I think option B is the most appropriate, as project controls need to align with program controls.
upvoted 0 times
...

Save Cancel