BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Practitioner Topic 3 Question 75 Discussion

Actual exam question for PRINCE2's PRINCE2-Practitioner exam
Question #: 75
Topic #: 3
[All PRINCE2-Practitioner Questions]

During stage 3, the team manager reports that the work to update the 'corporate quality procedures' has been completed and the product is ready to be delivered.

What should project assurance do next?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Johnetta
19 days ago
Haha, this is a classic project management question. I'd go with C, but B is also a valid option. 'Approved' is the magic word here.
upvoted 0 times
...
Antonio
21 days ago
This is a no-brainer. Option C is the correct answer. Approving the products is the key priority here.
upvoted 0 times
...
Theron
24 days ago
I think D is the right answer. Updating the stage plan to show the work package as completed is a logical next step.
upvoted 0 times
Dorethea
2 days ago
But shouldn't we also check the work package and follow the procedure to deliver completed products?
upvoted 0 times
...
Dick
8 days ago
I agree, updating the stage plan makes sense.
upvoted 0 times
...
...
Suzan
24 days ago
B is the way to go. Checking the work package and following the procedure is the standard process to deliver completed products.
upvoted 0 times
...
Loren
28 days ago
Option C seems to be the most appropriate choice. Verifying that all the products to be delivered are approved is a crucial step to ensure the quality of the project.
upvoted 0 times
Tawanna
1 days ago
C) Verify that all the products to be delivered by the work package are approved.
upvoted 0 times
...
Lindsey
3 days ago
B) Check the work package and follow the procedure to deliver completed products.
upvoted 0 times
...
Maxima
16 days ago
A) Update the team plan to show that the work package is complete.
upvoted 0 times
...
...
Truman
1 months ago
But shouldn't project assurance also verify that all the products to be delivered are approved?
upvoted 0 times
...
Galen
2 months ago
I agree with Lynna. It's important to keep the team plan updated.
upvoted 0 times
...
Lynna
2 months ago
I think project assurance should update the team plan to show that the work package is complete.
upvoted 0 times
...

Save Cancel